New Construction Plumbing Checklist
Plumbing · 11/02/2026
1Project & jurisdictionTwo values on this sheet have no national answer, your AHJ sets them.Nothing set
JurisdictionTest values on this checklist are from the 2021 International Plumbing Code. Adoption is a local decision, some states use the Uniform Plumbing Code, several use neither, and editions in force range from 2009 to 2024. Confirm with your authority having jurisdiction.Not set, several values depend on it
Site addressNothing set
Company detailsNothing set
2PhasesAuto-scoredUnderground through final, with the tests each phase requires.Nothing recorded yet
Underground / groundworkNot started
IPC 108.2 item 1, after trenches are excavated and bedded and piping installed, BEFORE any backfill is placed.
IPC 312.6 - 10 ft head, for 15 minutes.
IPC 312.7 - value per system, for 15 minutes.
Water serviceNot started
Not a model-code inspection. Most jurisdictions call it separately, with the trench open from the building to the main.
Rough-in / top-outNot started
IPC 108.2 item 2, after roof, framing, fireblocking, firestopping, draftstopping and bracing are in place and all piping is roughed in, BEFORE wall or ceiling membranes.
IPC 312.2 - 10 ft head, not less than 15 minutes.
IPC 312.3 - 5 psi, not less than 15 minutes.
Plastic piping shall not be tested using air.
IPC 312.5 - value per system, not less than 15 minutes.
IPC 312.9 - 2 in depth, not less than 15 minutes.
Gas pipingNot started
Not a model-code plumbing inspection. Test pressure and duration vary by jurisdiction more than any other value on this sheet.
Final / trim-outNot started
IPC 108.2 item 3, after the building is complete, all fixtures set and connected, and the structure ready for occupancy.
IPC 312.4 - 1 in water column, not less than 15 minutes.