New Construction Plumbing Checklist
Plumbing · 09/11/2026
1Project & jurisdictionTwo values on this sheet have no national answer — your AHJ sets them.Nothing set
JurisdictionTest values on this checklist are from the 2021 International Plumbing Code. Adoption is a local decision — some states use the Uniform Plumbing Code, several use neither, and editions in force range from 2009 to 2024. Confirm with your authority having jurisdiction.Not set — several values depend on it
Site addressNothing set
Company detailsNothing set
2PhasesAuto-scoredUnderground through final, with the tests each phase requires.Nothing recorded yet
Underground / groundworkNot started
IPC 108.2 item 1 — after trenches are excavated and bedded and piping installed, BEFORE any backfill is placed.
IPC 312.6 — 10 ft head, for 15 minutes.
IPC 312.7 — value per system, for 15 minutes.
Water serviceNot started
Not a model-code inspection. Most jurisdictions call it separately, with the trench open from the building to the main.
Rough-in / top-outNot started
IPC 108.2 item 2 — after roof, framing, fireblocking, firestopping, draftstopping and bracing are in place and all piping is roughed in, BEFORE wall or ceiling membranes.
IPC 312.2 — 10 ft head, not less than 15 minutes.
IPC 312.3 — 5 psi, not less than 15 minutes.
Plastic piping shall not be tested using air.
IPC 312.5 — value per system, not less than 15 minutes.
IPC 312.9 — 2 in depth, not less than 15 minutes.
Gas pipingNot started
Not a model-code plumbing inspection. Test pressure and duration vary by jurisdiction more than any other value on this sheet.
Final / trim-outNot started
IPC 108.2 item 3 — after the building is complete, all fixtures set and connected, and the structure ready for occupancy.
IPC 312.4 — 1 in water column, not less than 15 minutes.