Calculator
Load Calculator
NEC 2023 Article 220 Part III, every load gets its own demand factor.
Size a residential service the way the inspector checks it, enter habitable floor area and appliance nameplates, pick the NEC standard or optional method, and get the calculated load in amps, the recommended service size, spare capacity, and a demand breakdown citing every article applied. Free, no signup.
Calculator
NEC 2023 Article 220 Part III, every load gets its own demand factor.
Calculated load
123.8 A
29,700 VA ÷ 240 V single-phase
| Load | Connected | Demand factor | Demand |
|---|---|---|---|
| General lighting & general-use receptaclesNEC 220.41 | 6,000 | 3 VA/ft² | - |
| Small-appliance branch circuits (2)NEC 220.52(A) | 3,000 | 1,500 VA each | - |
| Laundry branch circuits (1)NEC 220.52(B) | 1,500 | 1,500 VA each | - |
| Lighting & receptacle demandNEC Table 220.45 | 10,500 | First 3,000 VA @ 100% + 7,500 VA @ 35% | 5,625 |
| Cooking appliances (1)NEC Table 220.55 | 12,000 | Column C · 8 kW for 1 appliance | 8,000 |
| Electric clothes dryerNEC 220.54 | 5,000 | 100% of nameplate | 5,000 |
| Fastened-in-place appliances (4)NEC 220.53 | 8,100 | 75%, four or more | 6,075 |
| Air conditioningNEC 220.60 | 5,000 | 100%, larger of heat vs cool | 5,000 |
Built on the 2023 NEC (NFPA 70). Section numbers moved in that edition, general lighting is now 220.41 and the lighting demand table is Table 220.45. Your AHJ has the final say on the method and the numbers.
Enter the dwelling and its appliances
Habitable floor area drives the 3 VA/ft² general lighting load. Add the range, dryer, water heater, dishwasher, disposal, microwave, air conditioning, electric heat, and EV charger nameplates, extra cooking units, heat pump strips, and additional fastened appliances live in the advanced section.
Choose the standard or optional method
The standard method (NEC 220 Part III) applies a separate demand factor to every load group. The optional method (NEC 220.82) takes the first 10 kVA at 100% and the remainder at 40%, then adds the largest of the six heating and air-conditioning selections. Toggle between them and compare.
Read the load, the service size, and the breakdown
Get the calculated load in amps, total connected VA, demand-adjusted VA, the next standard service rating (100/125/150/200/225/300/400 A), spare capacity percentage, and a line-by-line table showing each load, its NEC article, and the demand factor applied.
Habitable floor area drives the 3 VA/ft² general lighting load. Add the range, dryer, water heater, dishwasher, disposal, microwave, air conditioning, electric heat, and EV charger nameplates, extra cooking units, heat pump strips, and additional fastened appliances live in the advanced section.
The standard method (NEC 220 Part III) applies a separate demand factor to every load group. The optional method (NEC 220.82) takes the first 10 kVA at 100% and the remainder at 40%, then adds the largest of the six heating and air-conditioning selections. Toggle between them and compare.
Get the calculated load in amps, total connected VA, demand-adjusted VA, the next standard service rating (100/125/150/200/225/300/400 A), spare capacity percentage, and a line-by-line table showing each load, its NEC article, and the demand factor applied.
A dwelling never runs every appliance at once, so the NEC lets you discount the connected load before sizing the service. The standard method in Article 220 Part III does it load by load: general lighting and receptacles at 3 VA per square foot (220.41) plus two small-appliance circuits and a laundry circuit at 1,500 VA each (220.52), all pushed through the Table 220.45 tiers, first 3,000 VA at 100%, 3,001 to 120,000 VA at 35%, the remainder at 25%. Cooking equipment gets Table 220.55, which cuts a 12 kW range to an 8 kW demand load. Four or more fastened-in-place appliances drop to 75% (220.53), a dryer is the larger of 5,000 VA or nameplate (220.54), and only the larger of heating or air conditioning is carried because they are noncoincident (220.60).
The optional method in 220.82 trades precision for speed: pool the general loads and every appliance nameplate, take the first 10 kVA at 100% and everything above it at 40%, then add the largest of six heating and cooling selections, 100% of the air conditioning, 100% of a heat pump, a heat pump compressor plus 65% of supplemental strips, or resistance heat at 65% (fewer than four separately controlled zones) or 40% (four or more). It is only permitted on a 120/240 V or 208Y/120 V three-wire service rated 100 A or greater. Either method ends the same way: divide the calculated volt-amperes by 240, round up to the next standard rating, and confirm the 100 A minimum in 230.79(C). This calculator implements the 2023 edition of both methods and shows every article it applied, so you can hand the breakdown to a plan reviewer.
More free resources to help you price jobs, stay organized, and capture leads.
Free invoices, estimates, and work orders for your trade.
Browse templatesLet Crew answer every call while you focus on the job.
Learn moreGuides on pricing, hiring, marketing, and operations.
Read guidesState licensing requirements, exams, and renewal rules for electrical contractors.
View statesDiagnostics, installs and the odd bad attic, from contractors who film their own jobs.